Report on FEBT Rockhill Work Session of
September 27-28, 2003
Report by Lee Rainey

The eighth Rockhill work session of 2003 was held Saturday and Sunday, September 27-28, 2003. We had 25 volunteers on both days, making it our largest session ever. Fred and Kevin Kuhns of Memphis, TN again took the distance prize, narrowly edging out John and Barbara Morgan from Ontario.

Those participating included Fred Kuhns, Kevin Kuhns, Dick Ullery, Dean Mellander, Charlie Wootton, Jim Bacon, Chris Coleman, Pat Coleman, Ginny Rainey, John Morgan, Barbara Morgan, Alan Cupp, Jim Vliet, Bill Adams, Shawn Stauffer, Tom Kozub, Tom Diehl, Dennis Marquette, Wade Woodcock, Bob Goldby, Bud Goldby, Dan Cupper, Jim Sucke, Doug Linebaugh, Steve Jacobs, Don Schultz, Jane Clarke, Pete Clarke, Reggie Arford, and Lee Rainey.

TRACK 3
The crew finished inserting new ties into the trenches already dug, completed the spiking of all new ties, and made a start at leveling and aligning the track. In the meantime, an RTY crew put the switch at the south end of the track back into operation. The session ended by running the M-7 over all the new track to demonstrate what the crew had accomplished.

ELECTRICIAN'S SHOP
Working around torrential rains Friday and Saturday night, the crew installed the roof eave trim and south-end battens that had been prepainted at the last session. Final work was done on several windows. The surface preparation was completed and the building received a white primer coat on Saturday and a finish red coat on Sunday.

GLASS CREW
The glass crew as always was busy salvaging glass for the repairs in the main shops.

MAIN SHOPS
Some work was done at the double door of the main shops to prepare to insert the repaired sash. Chris Coleman finished installing this sash the day before the Spectacular.

All in all, with the help of the largest crew we have ever had, we met our two stretch objectives and finished our showcase projects for the Spectacular. It is quite a sight to see 25 people swarming over the yard working on various tasks and it's a sight we hope to repeat in the future!

The final East Broad Top Rockhill work session of 2003 will take place on Saturday and Sunday, November 1 and 2.


Posts: 57 | Registered: Jun 2002  |  IP: Logged | Report this post to a Moderator
   

Quick Reply
Message:

HTML is not enabled.
UBB Code™ is enabled.

Instant Graemlins
   


Post New Topic  Post A Reply Close Topic   Feature Topic   Move Topic   Delete Topic next oldest topic   next newest topic
 - Printer-friendly view of this topic
Hop To:


Contact Us | Home Page

Powered by Infopop Corporation
UBB.classic™ 6.7.2




Copyright © 2007-2016 TrainWeb, Inc. Top of Page|TrainWeb|About Us|Advertise With Us|Contact Us